How to use this app

  • Learn each section with pictures and plain-English summaries.
  • Try the calculators (EVM, PERT, Float, EMV, Channels) with your numbers.
  • Practice with section quizzes (instant explanations, progress saved).
  • Step-by-Step Labs teach CPM/EVM/Float from scratch with guided steps.

Tip: press t to toggle Dark/Light. Works fully offline.

1) Fundamentals & Diagrams

WBS

Network (PDM)

Gantt

RACI

DeliverablePMEngQAPO
RequirementsACIR
DesignIA/RCC
IncrementIRAC

2) Quality Charts

Pareto

Control Chart

Mean Sigma

3) Scheduling & Methods

Compression & Resources

  • Fast-tracking — overlap; rework risk ↑.
  • Crashing — add cost to shorten the critical path.
  • Leveling — respect limits; duration may change.
  • Smoothing — adjust within float; path unchanged.
  • Rolling wave — progressive elaboration.

Float Calculator

ES EF LS LF | Successor ES

4) EVM & Formulas (Interactive)

EVM Calculator

EV PV AC BAC

Practice

PERT, Channels, EMV

PERT: O M P
tₑ = (O + 4M + P)/6 · σ = (P − O)/6 · variance = σ²

Communication Channels — n(n−1)/2
Stakeholders n

EMV — sum(p×impact). One pair per line.

5) Agile & Flow

Burndown

Total Days

CFD

6) Business Analysis Models

Context Diagram

RTM Mini

Req IDDescriptionDesignTestDone?
R-01Login
R-02Search
R-03Export CSV

7) Glossary — Definitions & Real-World Use

8) Quizzes by Section

9) Step-by-Step Labs — CPM, EVM, Float

CPM Lab: Forward/Backward Pass

Network: A→B, A→C, B→D, C→D, D→E. Edit durations and compute ES/EF, LS/LF, Float, and the Critical Path.

Step 1 Forward pass: ES = max(EF of predecessors), EF = ES + Dur
Step 2 Backward pass: LF = min(LS of successors), LS = LF − Dur
Step 3 Floats: TF = LS − ES, FF = min(ES of successors) − EF. Critical path has TF = 0.

Durations — A B C D E
ActDurESEFLSLFTFFF

EVM Step-by-Step

Inputs EV (earned), PV (planned), AC (actual), BAC (budget at completion).
Formulas CV=EV−AC, SV=EV−PV, CPI=EV/AC, SPI=EV/PV, EAC=BAC/CPI, ETC=EAC−AC, VAC=BAC−EAC.

EV PV AC BAC

Float Mini-Lab

Goal Practice Free vs Total Float outside CPM.
Formulas FF = ESsucc − EF, TF = LS − ES = LF − EF.

Given Activity X: EF=; Successor ES=; Project finish=; Duration=; ES=.

Last updated 2025-08-15 21:39 UTC.